Environment Agency reports progress on £11m Somerset pump upgrades
The Environment Agency has reported progress on an £11 million programme to modernise six Somerset pumping stations. Two refurbishments are complete, with further works planned for 2027 and 2028.
Issued by Environment Agency, Somerset ·
The Environment Agency says refurbishment of pumps at Midelney and Huish Episcopi has been completed as part of an £11 million programme covering six pumping stations on the Somerset Levels and Moors.
Its 12 November update says Northmoor and Westover are next, with work planned for 2027. Long Load and North Drain are due to be completed in 2028.
The agency describes the replacement pumps as more reliable and energy efficient, with lower maintenance needs and less impact on fish and eels. The stations help manage winter floodwater and support summer irrigation. The remaining upgrades are planned work, and the programme does not remove all flood risk.
- Ends -
About Environment Agency
This is an attributed summary selected by FreePressReleases.uk, not submitted by or endorsed by the named organisation. See the original source above.